Case Details  Back
Deputy Commissioner Office Una

Zone/ Revenue Division Office : Headquarter Circle/ District Head Office : DC Office Una
Division/ Sub-Division/ Block Office/ In-Office Branch : Legal Branch Court Level : District
Court Name : District Courts Una Case Type Civil Suit
Nature Of Case : Recovery Matters Claim Brief : Suit for recovery Rs. 5,00,000 on account of damages/compensation for demolishing the protection /safety wall of the house of plaintiff and causing harassment by illegally constructing the road/passage /Gohri behind the house of plaintiff.
Case Filing Date : 16/11/2022 First Listing Date : 21/11/2022
Receiving Date : 28/11/2022 Reply to be Submitted by Date : 13/03/2024
Previous References (if any) :
Remarks By HOD :
Relief Sought:
Case Status : Pending Department As:
Case Entered By : Amit Kumar Sharma, IAS Case Entered Date :
Last Updated By : Last Updated Date :
Mark as important :
Huge Financial implications: Cascading effect :

 Hearings

 Replies Filed